Lower Plenty Building Upgrades

In the past year we have been working on significant upgrades to our Lower Plenty facility to make it more accessible and increase its fire resilience. These improvements will help us better serve our community for years to come.

Our accessibility and fire safety upgrades are well underway, with completion scheduled for mid-2026. This $3.5 million investment will transform how residents and staff experience the facility.

Key Updates:

Fire service upgrade is nearing completion, with two 189,000-litre water tanks installed and set to be commissioned in the coming weeks.

The David Bullard Hall (former Chapel, named in honour of a long-serving board member) has been levelled to a single floor, with the Baldacchino removed and covered. Doors have been installed and remedial painting is underway.

The lift shaft is complete, with glass installation scheduled for next week and lift installation to follow in mid-February.

Access ramps behind the hall and outside the clinical offices will be finished in the coming weeks. The front steps will then be demolished in early March to make way for the new front ramp.

The project will ultimately deliver ramps to three main entrances, an internal lift, new accessible bathrooms and toilets, a refurbished and levelled recreation hall floor, and upgraded fire tanks and pumps.

These disruptions haven’t been easy, and the noise levels have been challenging at times, but staff and residents have shown remarkable patience and adaptability in keeping our therapeutic environment strong throughout the construction.

Solar Power Expansion

Along with these building upgrades, we’re working to expand our solar power capacity to nearly triple our current 15kW system and adding battery storage. The project is estimated at $68,000, and we continue to seek funding support to make it a reality.

Additional solar panels and battery storage will reduce our reliance on the electricity grid, lower our carbon footprint, and provide more reliable energy in case of power outages and extreme weather events like the February 2024 storms that caused widespread power outages across Victoria.

Most importantly, reliable power means we can maintain consistent, accessible services for all residents and their families staying at the TC. Heating, cooling, lighting, and other essential equipment will remain operational regardless of grid disruptions or residents’ physical needs. The project will also reduce our reliance on a diesel backup generator, cutting both costs and emissions.

Energy savings, estimated at around $9,000 annually, can be reinvested into ad hoc programs for residents or contribute to our capacity to admit more people.